NázovKlientTechnológiaMiestoDátum
Yunus Emre Power plant (previously Adularya) revitalisation (2 x 145 MWe)Yildizlar Holding GroupCFB coal fired power plantTurkey, Ankara region5.2023
Manufacturing drawings of the water heater for the CHELM cement plantEuro Energy SlovakiaManufacturing drawings of the water heaterSlovak republic9.2022
DECAGONE Project – ORC innovative technology development.Trinecke Zelezarny a.s., TrinecORCCzech republic, TŽ Trinec6.2022
Provision of Engineering Support TG8 Retrofit.Mondi ŠtětíDistrict Heating stationCzech republic, Štětí2.2022
A new source for the combined production of electricity and heat for the continuous operation of the Metallurgical Plant PJSC MMK.IEG, ŽDASBoilers, Turbogenerators, Turbocompresors, BoPRussia, Metallurgical Plant PJSC MMK5.2021
Due diligence report • Equipment for catalytic oxidation of waste • Equipment for the production of hydrogen and fuels from waste CEE Capital Gasification of wasteSlovak republic, Sereď4.2021
Various studies – optimisation of the DH stationClient not published not published yet8.2020
Construction supervision, role of FIDIC engineer for the Project in Zvolenska Teplarenska a.s., ZvolenZvolenska Teplarenska a.s., Zvolen Slovak republic, Zvolen5.2020
Elaboration of implementation, documentation for construction: “Recycling of waste paper for the purpose of paper production / testliner / - Bukoza Vranov nad TopľouBukoza Vranov nad Topľou Slovak republic, Vranov nad Topľou12.2019
P&ID´s assessment for Unit No. 3 & 4 of NPP EMO MochovceROEZ, a.s., LeviceNuclearSlovakia, Nitra1.2018