Assignment name
WtE Plant ZEVO Chotíkov (CZ) –Coordination, Commissioning and supervision activities for final client Plzeňská Teplárenská a.s. Finalization of the project after the contract resign in between Plzenská Teplárenská a.s. and ČKD
Name of the client
Plzeňská Teplárenská, a.s., Czech Republic
Short description
ZEVO Chotíkov – new Waste to Energy plant
Services provided by company
The plants commissioning oriented activities
- General commissioning management of all sub-suppliers.
- Advisory services for projects in execution (technical support during identification of operation failures, proposal for remediation, documentation check and review, operation results evaluation).
- Preparation and elaboration of commissioning documentation for project including commissioning procedures (chemical cleaning, steam blowing), performance tests procedures, operation manuals, manuals for repair and maintenance, staff training
- Commissioning (supervision, coordination and execution) activities for whole scope of supply of EPC Contractor (whole Power Plant).
Country, location within country
Czech Republic, Chotíkov
Date beginning/completion
5.2015 - 12.2016
Technology
Waste to Energy plant
Type of service
TA
Staff involved in the project
CENGER Martin
REDLI Karol
VIGH Lubos